FASA 1 - KEMAJUAN DITAPAK SEHINGGA 2 Oktober 2025

Enam (6) Lokasi 

PAKEJ KERJA

LOKASI

STATUS

SL01 KM0-KM42 (E2)

Plaza Tol Sedenak - PLUS Seksyen S4

SIAP 

SL02 KM42-KM95 9 (E2)

Plaza Tol Yong Peng (S) - PLUS Seksyen S3

SIAP  

SL04 KM142.7-KM217.3 (E2)

Plaza Tol Bukit Gambir - PLUS Seksyen S2

SIAP 

R&R Air Keroh (U) - PLUS Seksyen S2

SIAP 

CL01 KM263.6-KM310.8 (E2)

R&R Seremban (U)  - PLUS Seksyen C5

SIAP - menunggu SKP

CL02 KM0-KM46.7(E6)

R&R Dengkil (S) - PLUS Seksyen C6

SIAP 99% - menunggu TNB

Kemajuan Kerja Pembinaan (6 LOKASI KABIN)

Plaza Tol Sedenak (100%)

Plaza Tol Yong Peng (S) (100%)

Plaza Tol Bukit Gambir (100%)

R&R Ayer Keroh (U) (100%)

R&R Seremban (U) (100%) 

R&R Dengkil (S) (99%)

FASA 2 - KEMAJUAN DITAPAK SEHINGGA 2 Oktober 2025

Lapan (8) Lokasi 

PAKEJ KERJA

LOKASI

STATUS

CL04 KM456.8-KM460 (E1)

R&R Sungai Buloh

CL05 KM434.4-KM456.8 (E1)

Plaza Tol Lembah Beringin

CL06 KM339.3-KM401.1 (E1)

Plaza Tol Sungkai

CL07 KM275.0-KM339.3 (E1)

Plaza Tol Gopeng

NL02 KM52.0-KM107.9 (E1)

Plaza Tol Pendang

SIAP - akan memohon SKP

NL03 KM107.9-KM162.8 (E1)

Pejabat Wilayah Utara PLUS (Bertam)

SIAP - akan memohon SKP

NL04 KM162.8-KM219.6 (E1)

Plaza Tol Alor Pongsu

NL05 KM219.6-KM221.4 (E1)

Plaza Tol Kuala Kangsar


Kemajuan Kerja Pembinaan (8 LOKASI KABIN)

R&R Sungai Buloh 


Plaza Tol Gopeng

Plaza Tol Lembah Beringin


Plaza Tol Pendang (100%) 

Plaza Tol Sungkai

Pejabat Wilayah Utara PLUS (Bertam) (100%) 

Plaza Tol Alor Pongsu

Plaza Tol Kuala Kangsar