Repeater Station Progress
PROGRESS DATE: 04-11-2026
Region
All Regions
Southern
Central
Northern
Phase
All Phases
Phase 1
Phase 2
Status
All Statuses
Original Only
Currently Upgrading
SL01-Plaza Tol Sedenak
Phase: Phase 1
E2 • S4
Current Status:
Completed
Original Progress
100%
π 21-07-2023
π 19-03-2024
SL02- Plaza Tol Yong Peng (S)
Phase: Phase 1
E2 • S3
Current Status:
Completed
Original Progress
100%
π 19-06-2023
π 18-07-2024
SL04- Plaza Tol Bukit Gambir
Phase: Phase 1
E2 • S2
Current Status:
Completed
Original Progress
100%
π 16-11-2023
π 03-07-2024
SL04-R&R Ayer Keroh (U)
Phase: Phase 1
E2 • S2
Current Status:
Completed
Original Progress
100%
π 21-11-2023
π 03-07-2024
CL01- R&R Seremban (U)
Phase: Phase 1
E2 • C5
Current Status:
Completed
Original Progress
100%
π 07-12-2023
π 06-03-2024
CL02-R&R Dengkil (S)
Phase: Phase 1
E2 • C6
Current Status:
Completed
Original Progress
100%
π 07-12-2023
π 26-02-2026
NL02-Plaza Tol Pendang
Phase: Phase 2
E1 • N1
Current Status:
Completed-Awaiting SKP
Original Progress
100%
π 27-02-2025
π 21-03-2025
NL03-Pejabat Wilayah Utara PLUS:Bertam
Phase: Phase 2
E1 • N3/N7/N6
Current Status:
Completed-Awaiting SKP
Original Progress
100%
π 10-02-2025
π 20-03-2025
CL05-Lembah Beringin
Phase: Phase 2
E1 • C1
Current Status:
Earth Works / Hoarding / Fencing / Mainhole / Cabin Works / M&E / Installation TNB meter panel
Original Progress
84%
π TBD
π TBD
CL06 - Sungkai
Phase: Phase 2
E1 • C6
Current Status:
Earth Works / Fencing /Formwork / Cabin footing / Mainhole / rectification fencing / Ban / Concrete / Cabin Base & PU panel
Original Progress
63%
π TBD
π TBD
CL07 - Gopeng
Phase: Phase 2
E1 • N5
Current Status:
Earth Works / Fencing /Formwork / Cabin footing / Mainhole / Kerb Fencing / concrete stump
Original Progress
60%
π TBD
π TBD
NL04-Plaza Tol Alor Pongsu
Phase: Phase 2
E1 • N4
Current Status:
Earth Works / Hoarding / Fencing / Mainhole / TNB Submain cable
Original Progress
49%
π TBD
π TBD
NL05-Plaza Tol Kuala Kangsar
Phase: Phase 2
E1 • N5
Current Status:
Fabrication and Material Readiness
Original Progress
10%
π TBD
π TBD