Repeater Station Progress

PROGRESS DATE: 04-11-2026
Region
All Regions
Southern
Central
Northern
Phase
All Phases
Phase 1
Phase 2
Status
All Statuses
Original Only
Currently Upgrading

SL01-Plaza Tol Sedenak

Phase: Phase 1
E2 • S4
Current Status: Completed
Original Progress
100%
πŸ“… 21-07-2023 🏁 19-03-2024

SL02- Plaza Tol Yong Peng (S)

Phase: Phase 1
E2 • S3
Current Status: Completed
Original Progress
100%
πŸ“… 19-06-2023 🏁 18-07-2024

SL04- Plaza Tol Bukit Gambir

Phase: Phase 1
E2 • S2
Current Status: Completed
Original Progress
100%
πŸ“… 16-11-2023 🏁 03-07-2024

SL04-R&R Ayer Keroh (U)

Phase: Phase 1
E2 • S2
Current Status: Completed
Original Progress
100%
πŸ“… 21-11-2023 🏁 03-07-2024

CL01- R&R Seremban (U)

Phase: Phase 1
E2 • C5
Current Status: Completed
Original Progress
100%
πŸ“… 07-12-2023 🏁 06-03-2024

CL02-R&R Dengkil (S)

Phase: Phase 1
E2 • C6
Current Status: Completed
Original Progress
100%
πŸ“… 07-12-2023 🏁 26-02-2026

NL02-Plaza Tol Pendang

Phase: Phase 2
E1 • N1
Current Status: Completed-Awaiting SKP
Original Progress
100%
πŸ“… 27-02-2025 🏁 21-03-2025

NL03-Pejabat Wilayah Utara PLUS:Bertam

Phase: Phase 2
E1 • N3/N7/N6
Current Status: Completed-Awaiting SKP
Original Progress
100%
πŸ“… 10-02-2025 🏁 20-03-2025

CL05-Lembah Beringin

Phase: Phase 2
E1 • C1
Current Status: Earth Works / Hoarding / Fencing / Mainhole / Cabin Works / M&E / Installation TNB meter panel
Original Progress
84%
πŸ“… TBD 🏁 TBD

CL06 - Sungkai

Phase: Phase 2
E1 • C6
Current Status: Earth Works / Fencing /Formwork / Cabin footing / Mainhole / rectification fencing / Ban / Concrete / Cabin Base & PU panel
Original Progress
63%
πŸ“… TBD 🏁 TBD

CL07 - Gopeng

Phase: Phase 2
E1 • N5
Current Status: Earth Works / Fencing /Formwork / Cabin footing / Mainhole / Kerb Fencing / concrete stump
Original Progress
60%
πŸ“… TBD 🏁 TBD

NL04-Plaza Tol Alor Pongsu

Phase: Phase 2
E1 • N4
Current Status: Earth Works / Hoarding / Fencing / Mainhole / TNB Submain cable
Original Progress
49%
πŸ“… TBD 🏁 TBD

NL05-Plaza Tol Kuala Kangsar

Phase: Phase 2
E1 • N5
Current Status: Fabrication and Material Readiness
Original Progress
10%
πŸ“… TBD 🏁 TBD