MSAR Work Package Progress

PROGRESS DATE: 01-06-2026
All Regions
Southern
Central
Northern
JKR
100%
E3 • S4/S5/S6

PILOT-KM0-KM32

Start: 01-11-2020

End: 17-02-2022

100%
E3 • S4/S5/S6

OBSL00-KM4-35.44

Start: 20-05-2024

End: 06-08-2025

100%
E2 • S4/S5/S6

SL01-KM0-KM42

Start: 09-10-2021

End: 13-06-2023

100%
E2 • S4/S5/S6

OBSL01-KM19-KM42

Start: 22-05-2023

End: 25-08-2026

100%
E2 • S4/S5/S6

OBSL01-EXTENSION-KM3.3-KM18.5

Start: 24-03-2025

End: 19-09-2025

100%
E2 • S4/S5/S6

SL02-KM42-KM95

Start: 01-01-2024

End: 22-06-2024

100%
E2 • S3

SL03-KM95-KM142.70

Start: 19-01-2022

End: 22-09-2023

100%
E2 • S2

SL04-KM142.7-KM217.40

Start: 20-01-2022

End: 28-01-2024

100%
E2 • S1

SL05-KM217.3-KM263.5

Start: 19-01-2022

End: 16-08-2024

100%
E1 • C5

CL01A-KM263.6-KM288

Start: 01-08-2025

End: 30-10-2026

0%
E1 • C5

CL01B-KM288-KM310.8

Start: N/A

End: N/A

75%
E6 • C6

CL02B (1)-KM15.4-KM21

Start: 01-08-2025

End: 30-10-2026

0%
E1 • C4

CL03-KM0-KM31.3

Start: N/A

End: N/A

0%
E1 • C4

CL04-KM456.8-KM460

Start: N/A

End: N/A

100%
E1 • C3

CL05A-KM434.4-KM456.8

Start: 25-09-2024

End: 18-06-2025

0%
E1 • C4

CL05B-KM401.1-KM434.4

Start: N/A

End: N/A

0%
E1 • C2

CL06-KM339.3-KM401.1

Start: N/A

End: N/A

0%
E1 • C1

CL07-KM275-KM339.3

Start: N/A

End: N/A

0%
E1 • N5

NL05-KM219.6-KM275

Start: N/A

End: N/A

0%
E1 • N3/N7/N6 & N4/N5

NL04-KM162.8-KM219.6

Start: N/A

End: N/A

100%
E1 • N1/N2 & N3/N7/N6

NL03A-KM107.9-KM137.5

Start: 01-08-2025

End: 30-10-2026

100%
E1 • JKR

NL03A-KM134-KM136.8

Start: 01-08-2025

End: 30-10-2026

0%
E1 • N3/N7/N6

NL03B-KM137.5-KM162.8

Start: N/A

End: N/A

100%
E1 • N1/N2

NL02-KM52-KM107.9

Start: 11-09-2024

End: 25-02-2025

100%
E1 • N1/N2

NL01-KM24.3-KM52

Start: 19-09-2024

End: 12-02-2025

100%
E1 • JKR

NL01-KM1.15-KM24.31

Start: 19-09-2024

End: 12-02-2025

100%
E2 • S4/S5/S6

SLB01-CAUSEWAY

Start: 09-08-2023

End: 16-04-2024