PROGRESS DATE: 01-06-2026
Region
All Regions
Southern
Central
Northern
Phase
All Phases
Phase 1
Phase 2
Status
All Statuses
Original Only
Currently Upgrading
SL01-Plaza Tol Sedenak
Phase: Phase 1
E2 • S4
Current Status:
Completed
Original Progress
100%
π 21-07-2023
π 19-03-2024
SL02- Plaza Tol Yong Peng (S)
Phase: Phase 1
E2 • S3
Current Status:
Completed
Original Progress
100%
π 19-06-2023
π 18-07-2024
SL04- Plaza Tol Bukit Gambir
Phase: Phase 1
E2 • S2
Current Status:
Completed
Original Progress
100%
π 16-11-2023
π 03-07-2024
SL04-R&R Ayer Keroh (U)
Phase: Phase 1
E2 • S2
Current Status:
Completed
Original Progress
100%
π 21-11-2023
π 03-07-2024
CL01- R&R Seremban (U)
Phase: Phase 1
E2 • C5
Current Status:
Completed
Original Progress
100%
π 07-12-2023
π 06-03-2024
CL02-R&R Dengkil (S)
Phase: Phase 1
E2 • C6
Current Status:
Completed
Original Progress
100%
π 07-12-2023
π 26-02-2026
CL04-R&R Sungai Buloh
Phase: Phase 2
E1 • C3
Current Status:
No status update provided.
Original Progress
0%
π TBD
π TBD
NL02-Plaza Tol Pendang
Phase: Phase 2
E1 • N1
Current Status:
Completed-Awaiting SKP
Original Progress
100%
π 27-02-2025
π 21-03-2025
NL03-Pejabat Wilayah Utara PLUS:Bertam
Phase: Phase 2
E1 • N3/N7/N6
Current Status:
Completed-Awaiting SKP
Original Progress
100%
π 10-02-2025
π 20-03-2025